Europe’s Largest Battery Storage System Begins Operations
BW ESS has started commercial operations at phase one of its Hams Hall battery energy storage system (BESS) in the West Midlands, UK. The 350 MW / 1,243 MWh facility is Europe's largest BESS by storage capacity.
Located beside National Grid's Hams Hall substation, the project will help balance electricity demand and intermittent renewable generation, supporting renewable integration, grid resilience and energy security. Read Powering the Grid of Tomorrow.
It entered commercial operation 20 days after energisation, following work with Sungrow, Energy-IO, National Grid and NESO. A second phase will raise capacity to 400 MW / 1,424 MWh. At full capacity, it will be capable of supporting the electricity needs of around 1.3 million homes for up to 3.5 hours. Related reading: Resilience at the Grid Edge: Unlocking the Power of DER Data through Policy and Regulation.
“The project was built and commissioned on budget and ahead of schedule,” said Erik Strømsø, CEO and Co-Founder of BW ESS.
Source: BW BESS