Dominion Energy has installed 44 of the 176 planned turbines at its Coastal Virginia Offshore Wind (CVOW) project, with installation of the 45th underway, according to its October 30 third-quarter update.
The 2.6 GW project uses Siemens Gamesa 14 MW turbines. The first was installed in January 2026, and the project delivered its first power to the grid in March. Installation is being carried out by Charybdis, the first Jones Act-compliant wind turbine installation vessel. The project also highlights the importance of offshore cable maintenance to renewable power infrastructure.
Dominion reported that the project’s levelized cost of energy fell from USD 83/MWh to USD 62/MWh, as higher Renewable Energy Certificate revenues offset a gross generation cost unchanged at USD 100/MWh.
The first two offshore substations are commissioned. The third is expected to be energised by year-end 2026, while the final turbine is scheduled for installation by the end of 2027. The project adds to the wider development of renewable and distributed energy generation.
Source: offshorewind.biz