Soluna, Applied Digital Plan 50 MW Texas AI Data Center
USA – Soluna Holdings and Applied Digital have signed a definitive agreement to form a joint venture developing a 50 MW AI data center near Silverton, Texas, powered by wind generation and the electricity grid.
The Project Dorothy 3 facility would be co-located with the 150 MW Briscoe Wind Farm, providing 50 MW of critical IT capacity for artificial intelligence and high-performance computing (HPC).
Applied Digital would hold 51% of the venture and contribute development capital, while Soluna would retain 49% and provide land and power-related assets.
ChronoScale Holdings has signed a non-binding letter of intent to lease the facility.
John Belizaire, Soluna CEO, said: “We have said for a long time that the constraint in AI is energy access, not chips.”
The transaction is expected to close by year-end, subject to tax abatement approval and definitive agreements, as data center power infrastructure and grid capacity requirements grow.
Source: Soluna Holdings