Albert Dock, Hull, UK- The transformers were received in two shipments at Albert Dock in Hull.
Allelys has announced that they have provided the full-service solution to offload, deliver and install four transformers at Dogger Bank Wind Farm.
According to Allelys, the transformers were received in two shipments at Albert Dock in Hull, where the team lifted the vessels using a crane and shunted them to a storage location for transshipment to their girder frame trailer. They were then transported before the next shipment arrived.
“We were involved at every stage of the project from completing letter drops, organising street furniture removal and temporary traffic management, through to project management and engineering support. To achieve four deliveries on consecutive weekends is a testament to the team’s hard work and ensured that the operation was completed on time,” said Zac Smout, Senior Project Manager at Allelys.