INDIA - The Dhalkebar substation is an important milestone for Nepal’s hydropower sector.
T&D India has announced the commissioning of Nepal’s first 400kV GIS substation. The prestigious contract was awarded to Linxon (at that time ABB) by Nepal Electricity Authority (NEA) in December 2017. Linxon’s scope was to design, supply, install, test and commission the high voltage equipment for fifteen 400kV bays, three 315 MVA transformers and one reactor, including control protection and automation system, as well as all associated civil works.
In November 2020, the Dhalkebar substation was energized to full capacity by Linxon. During the inauguration ceremony in February 2021, NEA presented a certificate of commendation to Linxon India Pvt Ltd for its successful completion.
The Dhalkebar substation is an important milestone for Nepal’s hydropower sector.
Source: T&D India