CHILE - According to Efacec, this project aims to supply power to a new data processing center, still under construction.
Efacec is responsible for developing a new 110/23kV substation in the Colina region, which integrates a control system and electric power networks. It is a project that aims to supply power to a new data processing center, still under construction, with an estimated maximum power of 40MW.
According to Efacec, they will also be responsible for contributing to the expansion and strengthening of Chile’s national electricity system. This second contract is based on the expansion of the Runge, Molina Pumahue, Gorbea, Victoria and Picarte substations.
They conclude that their technology and know-how lead Chilean customers to trust Efacec for expansion and strengthening of the national electricity system.
Source: Efacec