Lydian Energy Brings 150 MW Utah Battery Storage Project Online
Lydian Energy has brought its 150 MW/600 MWh Faraday battery energy storage system (BESS) in Utah County, Utah, into commercial operation. The standalone, four-hour lithium iron phosphate (LFP) system began operating on September 18 and provides contracted storage capacity to PacifiCorp under a long-term agreement supporting Meta’s Eagle Mountain data center.
Located beside the 525 MW Faraday solar facility, the battery shares its substation and grid interconnection, allowing storage to be added using existing infrastructure. The project supports grid reliability and adds flexibility to electricity supply, highlighting the role of distributed energy storage and virtual power plants and distributed energy resource management in evolving power systems.
“Faraday BESS shows what a mature platform like Lydian’s can deliver,” said Kim Smith, Chief Operating Officer of Lydian.
The project reached commercial operation approximately 10 months after mobilization. A second phase could add 375 MW/1,500 MWh by the fourth quarter of 2028.
Source: Lydian Energy