VINCI Wins $477M in Brazil Transmission Projects
Cobra IS, a subsidiary of VINCI, has secured two public-private partnership (PPP) contracts to develop 140 km of high-voltage transmission lines in Brazil, with an investment of approximately $477 million (€430 million).
Awarded following auctions by Brazil’s electricity regulator, ANEEL, the contracts cover design, financing and construction, followed by 30 years of operation.
In São Paulo state, the first project includes a 22.3 km line and a substation, with construction expected to take up to 48 months. The second, in Paraná state, covers a 116.5 km line, one substation and extensions to two existing substations. Construction is scheduled to take up to 60 months.
The projects expand Cobra IS’s high-voltage line portfolio to nearly 3,000 km across eight PPP contracts, seven in Brazil and one in Australia. The developments add transmission capacity and associated substation infrastructure, areas central to grid resilience and substation protection and control, supporting long-term network development.
Source: VINCI